Wynyard Area 3
Taylor Wimpey North Yorkshire·Start 27 Jan 2026·335 units
Material lines
Required volume is the earthworks position; imported and exported are movements recorded to date.
- Required
- 0
- Imported
- 0
- Exported
- 0
- Outstanding
- 0
- Required
- 0
- Imported
- 0
- Exported
- 0
- Outstanding
- 0
Opportunities
1 opportunityRoute plans someone has engaged for this site's outstanding balances — from identified to converted.
Export · Subsoil · Regional earthworks contractor (off platform)
9,000m³
Last event 106d ago
Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.
Closed — Rates not competitive. Presented rate didn't beat the groundworker package rate. The dominant close reason across clients (62% of Persimmon closures) — kept visible so the pattern is learnable.
Counterparty rate came back above the division's current option.
Compliance
U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.
No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.
No materials management plan recorded for this site.
Budget & risk
Visible to Taylor Wimpey + Nexus onlyBudgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.
£ ——.——
per m³, muck-away
£ ——.——
per m³, delivered
£ ———,———
rate × 0 m³ outstanding
Comments & actions
- All excess spoil to be stockpiled for Wynyard Park use.
- MMP in place for transfer between site and SUDS.
Carried straight from the tracker's comments column — this is where the division's open actions actually live.