Propsect Farm
Taylor Wimpey North Yorkshire·Start 14 Apr 2025·475 units
Material lines
Required volume is the earthworks position; imported and exported are movements recorded to date.
- Required
- -56,685
- Imported
- 0
- Exported
- 0
- Outstanding
- 56,685
- Required
- -8,924
- Imported
- 0
- Exported
- 0
- Outstanding
- 8,924
Opportunities
1 opportunityRoute plans someone has engaged for this site's outstanding balances — from identified to converted.
Export · Topsoil · Highfield Farm (own division)
8,528m³
Last event 63d ago
- •Start date Apr 2027 — needs stockpiling or phasing to line up
Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.
Next action
Confirm Highfield earthworks programme with technical team
James · due 25 Aug 2026
Tighten this opportunity: Confirmed earthworks programme for Highfield Farm.
Counterparty named and engaged (own division), timing constraint understood; no external rate needed for an internal transfer.
Compliance
U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.
No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.
- Consultant
- RWO
- MMP issue no.
- G24063
- DoWCoP verification received
- Yes
- DoWCoP reference
- Prospect Fm, Darlington
- Site activities impacting MMP
- No
Budget & risk
Visible to Taylor Wimpey + Nexus onlyBudgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.
£ ——.——
per m³, muck-away
£ ——.——
per m³, delivered
£ ———,———
rate × 65,609 m³ outstanding