Marske Sands
Taylor Wimpey North Yorkshire·Start 22 Apr 2024·402 units
Material lines
Required volume is the earthworks position; imported and exported are movements recorded to date.
- Required
- -45,100
- Imported
- 0
- Exported
- 0
- Outstanding
- 45,100
- Required
- -15,493
- Imported
- 0
- Exported
- 0
- Outstanding
- 15,493
Opportunities
2 opportunitiesRoute plans someone has engaged for this site's outstanding balances — from identified to converted.
2,139m³
Last event 56d ago
- •Fill requirement is subsoil; topsoil needs a revised MMP
- •Partial route — 2,139 m³ of 45,100 m³
Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.
Next action
Request chemical testing results for Marske Sands arisings
George · due 28 Aug 2026
Tighten this opportunity: Chemical testing on the Marske Sands arisings.
Route exists (own division) but no counterparty engagement and no rate — potential by rule.
Export · Topsoil · Former sand quarry restoration scheme (off platform)
45,100m³
Last event 63d ago
- •Capacity comfortably exceeds the outstanding volume
Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.
Next action
Contact operator re permit conditions and gate fee
James
Tighten this opportunity: Permit conditions on imported topsoil; Gate fee — operator not yet contacted.
Candidate restoration scheme; permit conditions and gate fee unknown — potential by rule.
Compliance
U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.
No MMP recorded
60,593 m³ still to move with no materials management plan on the register.
No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.
No materials management plan recorded for this site.
Budget & risk
Visible to Taylor Wimpey + Nexus onlyBudgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.
£ ——.——
per m³, muck-away
£ ——.——
per m³, delivered
£ ———,———
rate × 60,593 m³ outstanding
Comments & actions
- All muck managaement in Wearmouth's (Groundworker) package
Carried straight from the tracker's comments column — this is where the division's open actions actually live.