Marske Sands

Taylor Wimpey North Yorkshire·Start 22 Apr 2024·402 units

Net cut60,593 m³4 routes found

Material lines

Required volume is the earthworks position; imported and exported are movements recorded to date.

Topsoil
Net cut
Required
-45,100
Imported
0
Exported
0
Outstanding
45,100
Exported 0 of 45,100 m³0%
x
TestingNot recorded
Subsoil
Net cut
Required
-15,493
Imported
0
Exported
0
Outstanding
15,493
Exported 0 of 15,493 m³0%
x
TestingNot recorded

Opportunities

2 opportunities

Route plans someone has engaged for this site's outstanding balances — from identified to converted.

QualifiedPotentialSite to siteStalled

Export · Topsoil · Norton Lodge (own division)

2,139m³

Last event 56d ago

CompatibilityViabilityLogistics
  • •Fill requirement is subsoil; topsoil needs a revised MMP
  • •Partial route — 2,139 m³ of 45,100 m³
Not yet captured

Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.

Next action

Request chemical testing results for Marske Sands arisings

George · due 28 Aug 2026

Tighten this opportunity: Chemical testing on the Marske Sands arisings.

Route exists (own division) but no counterparty engagement and no rate — potential by rule.

IdentifiedPotentialRestorationStalled

Export · Topsoil · Former sand quarry restoration scheme (off platform)

45,100m³

Last event 63d ago

CompatibilityViabilityLogistics
  • •Capacity comfortably exceeds the outstanding volume
Not yet captured

Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.

Next action

Contact operator re permit conditions and gate fee

James

Tighten this opportunity: Permit conditions on imported topsoil; Gate fee — operator not yet contacted.

Candidate restoration scheme; permit conditions and gate fee unknown — potential by rule.

Compliance

U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.

Alerting as atPrototype control — the seeded exemptions expire May 2028.
  • No MMP recorded

    60,593 m³ still to move with no materials management plan on the register.

U1 exemption
Registered use of waste in construction. Three-year term, no renewal reminder from the regulator.
Not registered

No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.

MMP / DoWCoP
Materials management plan and CL:AIRE Definition of Waste Code of Practice verification.
No MMP

No materials management plan recorded for this site.

Budget & risk

Visible to Taylor Wimpey + Nexus only

Budgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.

Budgeted rate and exposure
Placeholder values — the prototype ships no real rate data. Scope: Muck-away and import, ex-works, excluding testing.
Budgeted removal rate

£ ——.——

per m³, muck-away

Budgeted import rate

£ ——.——

per m³, delivered

Exposure on outstanding balance

£ ———,———

rate × 60,593 m³ outstanding

Comments & actions

  • All muck managaement in Wearmouth's (Groundworker) package

Carried straight from the tracker's comments column — this is where the division's open actions actually live.