Bishops Vale
Taylor Wimpey North Yorkshire·Start 6 Jan 2025·48 units
Material lines
Required volume is the earthworks position; imported and exported are movements recorded to date.
- Required
- -1,945
- Imported
- 0
- Exported
- 1,680
- Outstanding
- 265
- Required
- -4,709
- Imported
- 0
- Exported
- 3,753
- Outstanding
- 956
Opportunities
1 opportunityRoute plans someone has engaged for this site's outstanding balances — from identified to converted.
Export · Subsoil · Off-site inert recovery (off platform)
1,150m³
Last event 62d ago
Client current, budgeted and presented rates land here once obtained. Placeholder values — the prototype ships no real rate data.
Next action
Get gate fee in writing for the remaining balance
George · due 22 Aug 2026
Tighten this opportunity: Gate fee confirmation.
Counterparty engaged and moving; waste transfer notes evidence two completed movements.
Compliance
U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.
No MMP recorded
1,221 m³ still to move with no materials management plan on the register.
- Reference
- WEX452908
- Registered
- 27 May 2025
- Expires
- 26 May 2028Expires in 20 months
- Site activities impacting exemption
- No
No materials management plan recorded for this site.
Budget & risk
Visible to Taylor Wimpey + Nexus onlyBudgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.
£ ——.——
per m³, muck-away
£ ——.——
per m³, delivered
£ ———,———
rate × 1,221 m³ outstanding
Comments & actions
- From QS Information
Carried straight from the tracker's comments column — this is where the division's open actions actually live.