Oaklands

Taylor Wimpey North Yorkshire·Start 25 May 2022·97 units

Net cut169 m³

Material lines

Required volume is the earthworks position; imported and exported are movements recorded to date.

Topsoil
Net cut
Required
-3,334
Imported
0
Exported
3,334
Outstanding
0
Exported 3,334 of 3,334 m³100%
x
TestingNot recorded
Subsoil
Net fill
Required
3,165
Imported
3,165
Exported
0
Outstanding
0
Imported 3,165 of 3,165 m³100%
x
TestingNot recorded

Opportunities

0 opportunities

Route plans someone has engaged for this site's outstanding balances — from identified to converted.

No opportunities mapped for this site yet.

Compliance

U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.

Alerting as atPrototype control — the seeded exemptions expire May 2028.
U1 exemption
Registered use of waste in construction. Three-year term, no renewal reminder from the regulator.
Not registered

No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.

MMP / DoWCoP
Materials management plan and CL:AIRE Definition of Waste Code of Practice verification.
No MMP

No materials management plan recorded for this site.

Budget & risk

Visible to Taylor Wimpey + Nexus only

Budgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.

Budgeted rate and exposure
Placeholder values — the prototype ships no real rate data. Scope: Muck-away and import, ex-works, excluding testing.
Budgeted removal rate

£ ——.——

per m³, muck-away

Budgeted import rate

£ ——.——

per m³, delivered

Exposure on outstanding balance

£ ———,———

rate × 0 m³ outstanding