Taylor Wimpey North Yorkshire·Start 26 Apr 2027·397 unitsPre-development

Net fill8,528 m³

Material lines

Required volume is the earthworks position; imported and exported are movements recorded to date.

Topsoil
Not known
Required
—
Imported
—
Exported
—
Outstanding
—
TestingNot recorded
  • • No earthworks position recorded.
Subsoil
Net fill
Required
8,528
Imported
0
Exported
0
Outstanding
8,528
Imported 0 of 8,528 m³0%
x
TestingNot recorded

Opportunities

0 opportunities

Route plans someone has engaged for this site's outstanding balances — from identified to converted.

No opportunities mapped for this site yet.

Compliance

U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.

Alerting as atPrototype control — the seeded exemptions expire May 2028.
  • No MMP recorded

    8,528 m³ still to move with no materials management plan on the register.

U1 exemption
Registered use of waste in construction. Three-year term, no renewal reminder from the regulator.
Not registered

No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.

MMP / DoWCoP
Materials management plan and CL:AIRE Definition of Waste Code of Practice verification.
No MMP

No materials management plan recorded for this site.

Budget & risk

Visible to Taylor Wimpey + Nexus only

Budgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.

Budgeted rate and exposure
Placeholder values — the prototype ships no real rate data. Scope: Muck-away and import, ex-works, excluding testing.
Budgeted removal rate

£ ——.——

per m³, muck-away

Budgeted import rate

£ ——.——

per m³, delivered

Exposure on outstanding balance

£ ———,———

rate × 8,528 m³ outstanding