Highfield Farm
Taylor Wimpey North Yorkshire·Start 26 Apr 2027·397 unitsPre-development
Material lines
Required volume is the earthworks position; imported and exported are movements recorded to date.
- Required
- —
- Imported
- —
- Exported
- —
- Outstanding
- —
- • No earthworks position recorded.
- Required
- 8,528
- Imported
- 0
- Exported
- 0
- Outstanding
- 8,528
Opportunities
0 opportunitiesRoute plans someone has engaged for this site's outstanding balances — from identified to converted.
No opportunities mapped for this site yet.
Compliance
U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.
No MMP recorded
8,528 m³ still to move with no materials management plan on the register.
No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.
No materials management plan recorded for this site.
Budget & risk
Visible to Taylor Wimpey + Nexus onlyBudgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.
£ ——.——
per m³, muck-away
£ ——.——
per m³, delivered
£ ———,———
rate × 8,528 m³ outstanding