All sites

Berrymead Farm

Taylor Wimpey North Yorkshire·Start 1 Aug 2022·123 units

Net cut13,200 m³

Material lines

Required volume is the earthworks position; imported and exported are movements recorded to date.

Topsoil
Net cut
Required
-11,200
Imported
0
Exported
11,200
Outstanding
0
Exported 11,200 of 11,200 m³100%
x
TestingNot recorded
Subsoil
Net cut
Required
-2,000
Imported
0
Exported
2,000
Outstanding
0
Exported 2,000 of 2,000 m³100%
x
TestingNot recorded

Opportunities

0 opportunities

Route plans someone has engaged for this site's outstanding balances — from identified to converted.

No opportunities mapped for this site yet.

Compliance

U1 exemption register and MMP / DoWCoP status. Pulled from Nexus Assurance where the client uses it; entered here otherwise.

Alerting as atPrototype control — the seeded exemptions expire May 2028.
  • DoWCoP verification report not received

    MMP 2563_2 issued by Lithos; verification outstanding.

U1 exemption
Registered use of waste in construction. Three-year term, no renewal reminder from the regulator.
Not registered

No U1 exemption on the register for this site. If material is being re-used on site under an exemption, it is not recorded here — the spreadsheet's silent failure mode.

MMP / DoWCoP
Materials management plan and CL:AIRE Definition of Waste Code of Practice verification.
Awaiting verification
Consultant
Lithos
MMP issue no.
2563_2
DoWCoP verification received
No
DoWCoP reference
Berrymead Farm, Darlington
Site activities impacting MMP
No

Budget & risk

Visible to Taylor Wimpey + Nexus only

Budgeted rate per m³ and computed exposure against the outstanding balance. Budgeted rates are ring-fenced to the client and Nexus. They never appear in cross-client output, benchmarks or shared fixtures.

Budgeted rate and exposure
Placeholder values — the prototype ships no real rate data. Scope: Muck-away and import, ex-works, excluding testing.
Budgeted removal rate

£ ——.——

per m³, muck-away

Budgeted import rate

£ ——.——

per m³, delivered

Exposure on outstanding balance

£ ———,———

rate × 0 m³ outstanding

Comments & actions

  • Multiple contractors, consortium muck, 1000m3 tw responsibility - import no longer required

Carried straight from the tracker's comments column — this is where the division's open actions actually live.